Client Background
The Nigerian National Petroleum Corporation (NNPC) is the nation’s foremost oil and gas entity,
with operations that demand consistently reliable, large-scale power infrastructure. For one of its
most ambitious power initiatives, NNPC sought a partner capable of delivering a complex,
high-capacity Independent Power Plant (IPP) with precision and speed.

The Challenge
NNPC required a robust 17.2MW power solution to be engineered and installed within a
compact 649-square-meter footprint. The project demanded not only technical excellence but
also rapid logistical execution — transporting massive generator units from Lagos to Abuja on a
tight timeline, all while maintaining zero tolerance for delays or safety incidents.

No video or image available for this project.

The Solution Mikano Power designed and delivered a fully synchronized IPP using low-speed WÄRTSILÄ generator technology:

4 units of WÄRTSILÄ generators, each operating at 750 rpm, engineered for a 25-year lifespan

4 units of WÄRTSILÄ generators, each operating at 750 rpm, engineered for a 25-year lifespan

Fully synchronized configuration for continuous, reliable power generation

Fully synchronized configuration for continuous, reliable power generation

Compact footprint design (649 m2) to maximize space efficiency

Compact footprint design (649 m2) to maximize space efficiency

Complex logistics execution — transporting all four generator units from Lagos to Abuja in just 10 days

Complex logistics execution — transporting all four generator units from Lagos to Abuja in just 10 days

Full engineering and project management oversight, delivered safely, on schedule, and with zero incidents

Full engineering and project management oversight, delivered safely, on schedule, and with zero incidents

Technical Highlights

4 × WÄRTSILÄ Generators

4 × WÄRTSILÄ Generators

Total Installed Capacity: 17.2 MW

Total Installed Capacity: 17.2 MW

Engine Speed: 750 rpm (low-speed design)

Engine Speed: 750 rpm (low-speed design)

Design Lifespan: 25 years

Design Lifespan: 25 years

Footprint: 649 m²

Footprint: 649 m²

Fully Synchronized Configuration

Fully Synchronized Configuration

The Results
Mikano Power successfully delivered one of Nigeria's landmark Independent Power Plant
projects, providing NNPC with a reliable, high-capacity power solution built for long-term
performance. Despite complex engineering and logistical requirements, the project was
completed safely, on schedule, and without incident. This achievement further demonstrates
Mikano's capability to execute complex utility-scale power projects and reinforces its position as
a trusted engineering partner for critical national infrastructure.